All
- All
As work increases along the alignment, the Purple Line team remains committed to keeping everyone safe. Pedestrians and motorists are advised to follow construction signage and use the open sidewalk(s). For the safety of the public and our construction team, entry into construction work zones is not permitted.
- All
Landscape, erosion and sediment control, and site maintenance along the Purple Line alignment will be conducted on an as needed basis weekdays and weekends from 7 a.m. to 7 p.m.
Bethesda/Chevy Chase
- Bethesda/Chevy Chase
Excavation for the shaft to connect to Metro's Red Line in Bethesda will continue through March 2025. This operation will include blasting the rock within the shaft located at the work zone on Elm Street at Wisconsin Avenue. Blasting is planned during daytime hours with additional work in the area occurring over multiple shifts between excavation and removal of spoils from the site. In advance of each blast, warning horn will be activated. Use of backup alarms will be limited during nighttime hours. Work may occur in two shifts weekdays and weekends, as needed.
- Bethesda/Chevy Chase
Crews continue work at the Purple Line Bethesda Station located at Elm Street and Wisconsin Avenue. A long-term lane closure of the southbound right lane of Wisconsin Avenue at Elm Street will continue through completion of the station construction to facilitate a work zone buffer and construction access. Pedestrians will need to use the signed pedestrian detour to access the northbound side of Wisconsin Avenue. Work will occur in two shifts from 7 a.m. to 5 p.m. and 5 p.m. to 7 a.m., weekdays and weekends, as needed. View detour here
- Bethesda/Chevy Chase
Crews continue utility work on Chevy Chase Lake Drive. This work will, at times, require temporary lane closures on Chevy Chase Lake Drive. Access will be maintained at all times for both vehicles and pedestrians around the work zone. On-street parking directly adjacent to the work zone will be limited. Please follow the posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed through November.
- Bethesda/Chevy Chase
Crews continue construction of walls, utilities and track installations along the former Georgetown Branch Trail between Elm Street Park and Rock Creek Park. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed through November.
- Bethesda/Chevy Chase
Crews continue work in the Jones Mill Road underpass area. Work includes utility relocations, construction of retaining walls and completing the west side of Jones Mill Road. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed through June 2025.
- Bethesda/Chevy Chase
The sidewalk along northbound Connecticut Avenue between Chevy Chase Lake Drive and Manor Road remains closed. Pedestrians are directed to use the crosswalks and the sidewalk on the southbound side of Connecticut Avenue. Please follow on-site signage. The closure is expected to be in place until December 2024. View detour here
- Bethesda/Chevy Chase
Work continues in the area of the Connecticut Avenue Purple Line station. Work includes utility installations, retaining walls and station elements. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
College Park
- College Park
On or about November 22, 2024, crews will implement a traffic shift on Campus Drive near River Road. The shift will reduce the travel lanes and may result in delays. The College Park Metro parking garage entrance will shift temporarily to the east. However, the garage will remain open and accessible at all times. The traffic shift is necessary to complete track installation from Campus Drive to the Metro station area. Pedestrian and bicycle access along Campus Drive will be maintained. Please follow onsite signage. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed. View detour here
- College Park
The temporary traffic shift on Adelphi Road at Campus Drive will continue through January 2025. Northbound Adelphi Road is reduced to one through lane at the intersection. Left turns from north and southbound Adelphi Road onto Campus Drive are eliminated during this time. This traffic shift is to facilitate track construction across the intersection. Please follow posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed. View detour here
- College Park
A long-term road closure of Rossborough Lane between Route 1 and Diamondback Drive continues. The closure is to complete stormwater drainage system installation and roadway reconfiguration and the construction of the Baltimore Avenue - UMD Station. Local access is maintained, and vehicular and pedestrian detours are in place. Please follow posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed.
- College Park
Crews continue to work on the Purple Line College Park-UMD Station. Pedestrian detours may occur intermittently near the station site. Please follow posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed.
- College Park
The long-term traffic configuration on Campus Drive between Diamondback Drive and River Road remains in effect. Traffic is shifted to the north side of Campus Drive with one lane in each direction maintained. A signed pedestrian detour has been implemented to maintain pedestrian access around the work zone. This traffic pattern will be in place until approximately December 2024.
Glenridge/New Carrollton
- Glenridge/New Carrollton
On or about November 13, 2024, crews will close Emerson Place at Ellin Road for approximately one month. This closure is in place to install tracks and complete roadway reconstruction. Once the track installation is complete, Ellin Road will open from Emerson Place to Hanson Oaks Drive. This configuration will allow two-way traffic between Emerson Place and Veterans Parkway. Please follow all on-site signage. Work may occur from 7 a.m. to 7 p.m., weekdays and weekends, as needed. View detour here.
- Glenridge/New Carrollton
Ellin Road remains closed between Hanson Oaks Drive and Emerson Place. Residential access to Emerson Place will be maintained via Harkins Road to Ellin Road. Hanson Oaks Drive will be accessible via Veterans Parkway (MD 410) to Ellin Road. This configuration will remain in place through fall of 2024.
- Glenridge/New Carrollton
Phased traffic shifts of Annapolis Road (MD 450) and Veterans Parkway (MD 410) continue to facilitate Purple Line track installation across Annapolis Road through the Glenridge Station. Two through lanes and dedicated left turn lanes will be maintained during each phase. Pedestrian detours may occur as the work progresses. Please follow signage and use caution around the established work zones. Work may take place from 7 a.m. to 7 p.m., weekdays and weekends as needed.
Greater Lyttonsville/Woodside
- Greater Lyttonsville/Woodside
Crews continue wall construction, stormwater drainage installation and other utility work adjacent to the CSX/Metro tracks between Talbot Avenue and the Silver Spring Transit Center. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- Greater Lyttonsville/Woodside
Crews continue retaining wall construction and utility installation along the alignment from Rock Creek to Talbot Avenue. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- Greater Lyttonsville/Woodside
Construction continues at the Lyttonsville Station and operations and maintenance yard located adjacent to the Lyttonsville Place Bridge. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
Long Branch
- Long Branch
No left turns from Barron Street onto Piney Branch Road continue until approximately November 7, 2024. This traffic restriction is in place to allow crews to install tracks in a work zone established in the center of Piney Branch Road. Please follow all on-site signage. Work may occur from 7 a.m. to 7 p.m., weekdays and weekends, as needed.
- Long Branch
The long-term closure of Arliss Street between Piney Branch Road and Garland Avenue continues. This closure allows crews to install utilities and construct the Long Branch Station. A temporary driveway has been constructed to the Flower Branch Apartments, and a detour for vehicles and pedestrians is in place. The Long Branch Library will be accessed by turning north on Flower Avenue and east on Plymouth Street. Please follow the posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed through fall 2024. View detour here
- Long Branch
Crews will maintain a minimum of one lane in each direction on Piney Branch Road (MD 320) between Greenwood Avenue and University Boulevard (MD 193) for construction of the Purple Line. Activities include track installation, sidewalks, curb and storm drains. Pedestrian access will be maintained using temporary detours; please follow onsite signage. Access to driveways and businesses will be maintained. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed.
- Long Branch
Crews continue work on the Plymouth Tunnel and the Manchester Place Station. Work includes construction of the west portal at Wayne Avenue, utility work and preparation for track installation within the tunnel. The work zone for the upper section of the Manchester Place Station located on Plymouth Street in Silver Spring will be accessed via Plymouth Street, and residential parking will not be impacted. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
Riverdale Park
- Riverdale Park
Mustang Drive is now open at Riverdale Road. Eastpine Drive at Riverdale Road is closed to be reconstructed as a cul-du-sac. Access to the community will be maintained from the signalized intersections at Mustang Drive and 64th Avenue. Work may occur from 7 a.m. to 7 p.m., weekdays and weekends, as needed. View detour here
- Riverdale Park
A work zone in the center of Kenilworth Avenue from River Road to East-West Highway to allow track installation remains in effect. Left turns are restricted onto Kenilworth Avenue from Rittenhouse Street (eastbound) and from Rittenhouse Street onto Kenilworth Avenue (westbound). This restriction will be in place until December 2024. Work may occur from 7 a.m. to 7 p.m., weekdays and weekends, as needed. View detour here
- Riverdale Park
66th Avenue at Riverdale Road is temporarily closed until January 2025. This closure allows track installation across 66th Avenue and the reconstruction of sidewalks. Work typically occurs from 7 a.m. to 7 p.m. but may continue nights and weekends, as necessary. Pedestrian access will be maintained. Please follow all posted signage.
- Riverdale Park
67th Place at Riverdale Road is permanently closed and will be reconfigured into a cul-de-sac. Pedestrians will be temporarily required to use 67th Avenue to access Riverdale Road. Please follow all posted signage.
- Riverdale Park
Intermittent nightly closure of the intersection of East - West Highway and Kenilworth Avenue will continue Sunday night through Thursday night from 9 p.m. to 5 a.m. through December 2024. Right-hand turn lanes will be open from East-West Highway and Kenilworth Avenue. Through traffic will be required to use the approved detours as detailed. This closure is necessary to complete the bridge and install overhead safety overhangs. During this time, operations at night will include tightening and installing steel bolts to the bridge girders, which will generate additional noise. View detour here
- Riverdale Park
The long-term traffic shift on Riverdale Road (MD 410) between the Baltimore-Washington Parkway and Veterans Parkway (MD 450) to allow the construction of the Beacon Heights-East Pines Station continues. The travel lanes have been shifted to the north. Two lanes in each direction and pedestrian access will be maintained. View detour here
- Riverdale Park
Work continues along Kenilworth Avenue (MD 201) between River Road and the East-West Highway (MD 410) through spring 2025. Work includes stormwater drainage installation and roadway work in preparation for track installation. Access to driveways, businesses and bus service will be maintained. All on-street parking has been eliminated and vehicles will be towed at the owner's expense. Work may occur 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- Riverdale Park
Crews continue work on the Purple Line alignment adjacent to River Road from the College Park Metro Station to Kenilworth Avenue. Pedestrian detours may occur intermittently. Please follow posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed.
- Riverdale Park
Crews continue work on the Riverdale Park-Kenilworth elevated station located at the corner of Riverdale Road (MD 410) and Kenilworth Avenue (MD 201). The work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed, weather permitting.
- Riverdale Park
Crews continue work along Riverdale Road (MD 410) between Kenilworth Avenue and Veterans Parkway. Lane closures may be implemented on a daily basis. The work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed, weather permitting.
Silver Spring
- Silver Spring
On or about December 20, 2024, crews will temporarily close Manchester Road north of Wayne Avenue for approximately six weeks. Please follow all on-site signage. This closure will take place after Sligo Creek Parkway fully opens to traffic. The closure is necessary to allow track placement and the reconstruction of the intersection. Work may occur 7 a.m. to 7 p.m. weekdays and weekends. View detour here
- Silver Spring
On or about December 3, 2024, crews will temporarily close Mansfield Road at Wayne Avenue for approximately four weeks. Pedestrian access will be maintained. Please follow all on-site signage. This closure is necessary to allow track placement and the reconstruction of the intersection. Work may occur 7 a.m. to 7 p.m. weekdays and weekends as needed View detour
- Silver Spring
Sligo Creek Parkway will remain closed between Wayne Avenue and Schuyler Road until November 2024. During this closure, Wayne Avenue will be reduced to one travel lane in each direction to facilitate track placement and roadway reconstruction. Please follow all on-site signage associated with the detour. View detour here
- Silver Spring
Purple Line crews will continue periodic night work to complete sewer crossings on Bonifant Street in Silver Spring. Work will occur between 8 p.m. and 5 a.m. for approximately one month. A full closure of Bonifant Street will be necessary when work is in progress. Please follow all posted signage and detours.
- Silver Spring
A temporary traffic shift on Georgia Avenue (US 29) between Silver Spring Avenue and Wayne Avenue (MD 594A) remains in effect until January 2025. Travel will be reduced to two lanes in either direction and shift to the west around the work zone at Bonifant Street. This traffic shift will facilitate utility and track installation across Georgia Avenue. Pedestrian detours will be in place around the work zone. Please follow all posted signage. Work typically occurs from 7 a.m. to 7 p.m. but may continue nights and weekends, as necessary.
- Silver Spring
The Spring Street Bridge in Silver Spring will be closed through Spring 2025. During this time, crews will demolish the existing bridge and begin construction of the new bridge. The detour attached will be implemented during the closure. Please follow on-site signage. This operation will often require overnight work to meet the schedule and to accommodate CSX trains. We aim to prioritize noisy work to daytime hours whenever possible. View detour here
- Silver Spring
A new traffic pattern is in effect to establish a work zone on the south side of Wayne Avenue to complete the stormwater system, curb, and sidewalk installation. Pedestrians will be required to use the sidewalk on the north side of Wayne Avenue. More information here
- Silver Spring
Crews continue work on the Wayne Avenue bridge over Sligo Creek, including foundations for the new bridge, concrete, and stream restoration. The work may take place 5 a.m. to 10 p.m. weekdays and weekends, as needed.
- Silver Spring
Crews continue utility work on Ramsey Avenue between Wayne Avenue and Bonifant Street. The utility work will require traffic shifts and periodic lane closures but will remain accessible at all times. Pedestrians will be directed to use the sidewalk on the east side of Ramsey Avenue. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed.
- Silver Spring
Crews continue work on the Purple Line Silver Spring Library station located at the Brigadier General Charles E. McGee Library. Access to the library and businesses surrounding the library including Bonifant Street will be maintained at all times. ADA-compliant pedestrian access will be maintained to and around the library via Wayne Avenue and Fenton Street. Pedestrian pathways may change intermittently around the work zone; please follow on-site signage. Fencing has been installed to delineate the work zone to allow excavation, utility relocations, systems, and trackwork. Access to Bonifant Street will remain one-way, eastbound from Georgia Avenue. Construction may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed through the end of 2024.
- Silver Spring
Crews implemented the long-term traffic configuration on Wayne Avenue (MD 595A) between Sligo Creek Parkway and Fenton Street, reducing the road to one lane in each direction for continued utility relocations, installation of stormwater systems and reconstruction of the curb, sidewalk, and roadway. Access to residents’ properties and driveways will be maintained, while street parking within the work zones is prohibited. Pedestrian access along Wayne Avenue will be maintained with at least one sidewalk open at all times. Please follow posted signage for pedestrian detours when applicable. Temporary lane closures may be implemented 9 a.m. to 3:30 p.m., weekdays and weekends, as needed.
- Silver Spring
Purple Line work will continue around the Paul S. Sarbanes Transit Center as crews continue construction of the Purple Line Station and the mezzanine to the Metro and MARC stations. ADA-compliant pedestrian access will be maintained with intermittent changes to walkways around the work zone; please follow on-site signage. Access to the transit center will be maintained at all times around the Purple Line work zone. Construction may occur 7 a.m. to 7 p.m., and 7 p.m. to 7 a.m. weekdays and weekends, as needed.
- Silver Spring
The pedestrian detour for the Sligo Creek Trail and Sligo Cabin Neighborhood Park remains in effect around the work zone and the adjacent parking lot. Please follow posted signage. Work may occur 7 a.m. to 7 p.m., weekdays and weekends, as needed through the end of 2024.
- Silver Spring
Crews continue construction on Wayne Avenue (MD 594A) from Sligo Creek Parkway to Flower Avenue. Temporary lane closures may occur 7 a.m. to 5 p.m., weekdays and weekends, as needed. Temporary sidewalk closures will occur as needed.
- Silver Spring
The long-term pedestrian detour remains in effect for the crosswalks across Georgia Avenue (MD 29) at Bonifant Street. Pedestrians will be directed to use the crosswalk located a block south at Thayer Avenue. Please follow posted signage for the pedestrian detour. Bonifant Street (East) will remain open to eastbound vehicular traffic and pedestrians. Access to all businesses along Bonifant Street will be maintained during construction. Construction will continue on Bonifant Street East and West through 2024. View detour here
- Silver Spring
Crews implemented the long-term lane closure of Bonifant Street (West) between Ramsey Avenue and Georgia Avenue that will remain in effect through the completion of construction. Pedestrian access will be maintained during the road closure. Pedestrians must obey construction signs and stay out of the work zone for their safety and the safety of the construction crew.
- Silver Spring
Crews continue work on Bonifant Street (east) between Georgia Avenue and Fenton Street with a focus on the north side of the roadway. Bonifant Street will be permanently reduced to one-way eastbound, with no parking permitted on the north side of the street. Any vehicles parked within the work zone will be towed at the owner’s expense. Crews continue to complete critical utility connections, storm drain installation, curb and sidewalk reconstruction followed by track installation through the fall of 2024. Once this work is complete, the north side of Bonifant Street will be open in the final configuration and the work zone will shift to the south side. Access to businesses, parking lots, and residential properties will be maintained by performing some construction activities outside of typical business hours, including nighttime construction, when needed. Flagging operations may be utilized during typical work hours, 7 a.m. – 7 p.m., weekdays and weekends as needed.
- Silver Spring
Crews continue work on the Plymouth Tunnel and the Manchester Place Station. Work will include construction of the west portal at Wayne Avenue, utility work and preparation for track installation within the tunnel. The work zone for the upper section of the Manchester Place Station located on Plymouth Street in Silver Spring will be accessed via Plymouth Street, residential parking will not be impacted. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- Silver Spring
Crews continue construction of walls and installation of utilities adjacent to the CSX/Metro tracks between Talbot Avenue and the Silver Spring Transit Center. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- Silver Spring
Stream restoration work for Sligo Creek near Wayne Avenue will continue through the end of 2024. In accordance with Maryland Department of the Environment regulations, a pumping operation is required at the work zone during the restoration work. Work may occur from 7 a.m. to 7 p.m. However, the pumping operation may require equipment to be in operation overnight. Efforts have been made to minimize the hours of operation and maintain sound levels under Montgomery County noise standards.
University Boulevard
- University Boulevard
The long-term traffic pattern on University Boulevard (MD 193) between Piney Branch Road (MD 320) and Carroll Avenue (MD 195) continues with a work zone in the middle of the roadway. Two lanes of traffic in each direction will be maintained on the outside lanes of University Boulevard. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- University Boulevard
The long-term traffic pattern on University Boulevard (MD 193) between New Hampshire Avenue (MD 650) and Riggs Road (MD 212) continues to establish a work zone in the middle of the roadway. Two lanes of traffic in each direction will be maintained on the outside lanes of University Boulevard. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- University Boulevard
The traffic pattern on University Boulevard (MD 193) from Phelps Road until Adelphi Road to establish a new work zone in the middle of the roadway on University Boulevard (MD 193) continues. Work may take place from 7 a.m. to 7 p.m., nights and weekends, as necessary. Pedestrian access will be maintained. Please follow all posted signage.
- University Boulevard
Overnight utility relocation and conduit installation work continues across University Boulevard (MD 193) between Piney Branch Road (MD 320) and Adelphi Road. This periodic work will require temporary lane closures and may occur 7 p.m. to 6:30 a.m. weekdays and weekends, as needed.
- University Boulevard
Crews continue work along University Boulevard (MD 193) between Piney Branch Road (MD 320) and New Hampshire Avenue. Lane closures may be implemented on a daily basis. Access to businesses and residential properties and pedestrian access will be maintained. Please follow onsite signage. Work may take place 7 a.m. to 7 p.m. weekdays and weekends, as needed.
- University Boulevard
Overnight utility relocation and conduit installation work continues across University Boulevard (MD 193) between Piney Branch Road (MD 320) and Adelphi Road. This periodic work will require temporary lane closures and may occur 7 p.m. to 6:30 a.m. weekdays and weekends, as needed.